Sustainable Development Office Targets
Sustainable Development Office Targets 2018 - 2022
Objective | Target | Achievement |
---|---|---|
To reduce electricity consumption |
Reduce electricity usage by 20% | 21.8% reduction |
To reduce gas consumption |
Reduce gas usage by 25% | 5.53% reduction * |
To reduce water consumption |
Reduce water usage by 20% | 47% reduction |
To reduce the amount of waste sent to landfill |
Increase the amount of waste recycled within Parliament Buildings to 85% ** | 66.4% recycling rate |
To reduce paper consumption |
Reduce paper consumption by 50% | 70.7% reduction |
To improve the Northern Ireland Assembly’s Environmental performance | To continue with the Employee Supported Volunteering and encourage staff to avail of it. | Ongoing |
To improve the Northern Ireland Assembly’s Environmental performance | To commit the Northern Ireland Assembly to participate in 3 specific challenges per year. | 29 challenges |
Sustainable Development Office Targets 2022 - 2023
Objective | Target | Status to date |
---|---|---|
To reduce electricity consumption | Reduce electricity usage by 35% from 2008/2009 figures | 29.4% reduction |
To reduce gas consumption | Reduce gas usage by 30% from 2008/2009 figures | 8.6% reduction |
To reduce the amount of waste sent to landfill | Reduce the amount of waste produced by 65% from 2008/2009 figures** | 51.6% reduction |
To reduce the amount of waste sent to landfill | Work towards UK Plastic Pact to reduce single use plastics by 2025 | Ongoing |
To reduce paper consumption | Reduce paper consumption by 85% from 2008/2009 figures | 81.5% reduction |
To improve the Northern Ireland Assembly's Environmental performance | To continue with the Employee Supported Volunteering and encourage staff to avail of it | Ongoing |
To improve the Northern Ireland Assembly's Environmental performance | To commit the Northern Ireland Assembly to participate in 6 specific challenges per year | 11 challenges |
* We had anticipated better gains from the roof project and the planned metering upgrade.
** Secondary segregation by the waste contractor means there is zero waste to landfill