Appendix 5: Other Evidence considered by the Committee

5.3 Northern Ireland Assembly Commission: Response dated 21 October 2021 - Budget 2020/21

An Ceann Comhairle
Seomra 39
Foirgnimh na Parlaiminte Baile Lias na Scath
Cnoc an Anfa
Beal Felrste, BT4 3XX
Guthan:+44 (0) 28 9052 1130
speakersoffice@niassembly.gov.uk

Northern Ireland Assembly

The Speaker
Room 39
ParliamentBuildings
Ballymiscaw
Stormont
Belfast, BT4 3XX
Tel:  +44 (0) 26  9052 1130
email: speakersoffice@nlassembly.gov .uk

Mr Daniel McCrossan

Chairperson of the Audit Committee

Room 325

Parliament Buildings

21 October 2021

Daniel a chara,

RE: ASSEMBLY COMMISSION: BUDGET 2021-22

I refer to your letter dated 29 September 2021 regarding the Audit Commi ttee's consideration of the Assembly Commission's budget for 2021-22 in light of the upcoming budget for 2022-25.

Your letter sought an update on work carried out and work outstanding against six specific projects namely:

  • Broadcasting infrastructure/systems
  • Improving Wi-Fi strength
  • TV/ TV Distribution System Replacement
  • Replacement of the Security Management System
  • Electronic Access Control
  • Improving accessibility/disabled access.

The table at Appendix 1 sets out the details for each of these items.

I trust that this update will assist the Audit Committee in its scrutiny of the Assembly Commission's budget for 2022-25.

Is mise le meas

Alex MAskey MLA

 

Area identified by Audit CommitteeCapital Budget Agreed 2021-22

£000
Capital Spend 2021-22 YTD

£000
Total Planned Spend 2021-22

£000
Comments

Broadcasting infrastructure/systems

£500

£13

£100

The substantive element of this stage of the upgrade of audio and video systems is now planned for summer recess 2022. It is anticipated that expenditure of approximately £100k on lighting and acoustic treatments (in broadcast-enabled rooms) in response to broadcasting surveys will be carried out in 2021-22.

Improving Wi-Fi strength

£0

£0

£0

While this was not identified in the capital expenditure plan for 2021- 22, the Assembly Commission intends to undertake a review of the system and to commence a project to replace the Wi-Fi network infrastructure before the end of the current Assembly mandate.

TV / TV Distribution System Replacement

£200

£0

£175

The procurement process will formally commence in late October/early November 2021, with the contract being awarded in December. Following market sounding, it is now anticipated that the costs for this project will be £175k (down from the original estimate of

£200k).

Replacement of the Security Management System

£280

£0

£0

It is planned that the procurement process for this project will commence in November 2021 with the contract being awarded in January 2022. It is now anticipated that the capital works (and associated capital expenditure) will take place in early 2022-23. The technical adviser to the project has advised that the cost of equipment is likely to have increased so an estimate of an additional £80k for the project has been made in the capital plan for 2022-23. However, this figure will be re-assessed once tender returns are received in late 2021/early 2022.

Electronic Access Control

£210

£0

£50

This project has linkages to the replacement of the Security Management System (noted above) as any access control solution will need to be integrated with the Security Management System. While it is estimated that £50k can be spent in 2021-22 on project advice and design, it is planned to proceed with the remainder of this project in 2022-23.

Improving accessibility/disabled access.

£50

£0

£0

While this was not specifically identified in the capital expenditure plan for 2021-22, a project to provide an additional two-way fire evacuation emergency communication system (estimated at £50k) was included. Outline proposals have been drafted for the emergency communication system but the limited availability of both the designated Fire Officer and a works designer means that expenditure is not now anticipated until 2022-23 (subject to agreeing the proposed scheme with the Fire Officer).

 

 

AUDIT COMMITTEE

Room 254 Parliament Buildings

Ballymiscaw Stormont Belfast BT4 3XX

Tel: 028 9052 1843

Email: committee.audit@niassembly.gov.uk

Mr Alex Maskey MLA

The Speaker

Chairperson of the Assembly Commission

Issued via email to: speaker@niassembly.gov.uk

30 September 2021

 

Dear Alex

Northern Ireland Assembly Commission: Budget 2021-22

At its meeting on 29 September 2021, the Audit Committee considered matters relating to the Northern Ireland Assembly Commission budget for the 2021-2022 period.

To assist its consideration of the Commission’s budget for the 2022-2025 period, the Committee agreed to request an update on the work that has been carried out, and details of the work outstanding, in relation to the following areas:

  • Broadcasting infrastructure/systems
  • Improving Wi-Fi strength
  • TV / TV Distribution System Replacement
  • Replacement of the Security Management System
  • Electronic Access Control
  • Improving accessibility/disabled access.

Details of the expenditure incurred to date in 2021-22 for each of the areas is also requested.

I would appreciate a response by 28 October 2021.

Yours sincerely

Daniel McCrossan

Chairperson of the Audit Committee

c.c Lesley Hogg, Richard Stewart, Robin Ramsey

Find MLAs

Find your MLAs

Locate MLAs

Search

News and Media Centre

Visit the News and Media Centre

Read press releases, watch live and archived video

Find out more

Follow the Assembly

Follow the Assembly on our social media channels

Keep up-to-date with the Assembly

Find out more

Useful Contacts

Contact us

Contacts for different parts of the Assembly

Contact Us